| Project
Photos
8/17/07: Remodels nearing completion
|
|
Finishing of exterior of new middle
school building.
|
New entry of the remodeled
library. |
|
|
View of the roof work being
done. |
New ceiling grid being installed
in lunchroom. |
7/06/07: Framing out the new spaces
|
|
The only remnant of the
head’s
office will
now
become part of one of the new second
grade
classrooms. |
Interior of the gym, temporary
housing for over
3,000 pieces from 59 former work and class
spaces,
moved in
approximately
ten days. |
|
|
The connection point between
the new Middle
School
and the library is made and windows
have
been installed. At the lower
right is the breezeway entering onto the playground. |
K-3 building gets seismic improvements,
followed
by a new roof! |
|
|
New main office area what
was formerly
the Middle School. |
New library classroom takes
shape. The new
building will connect to the library on the
left side of this
shot. |
6/15/07: Library Demo

Wall between
Library, Viewing Room,
and
landing is removed (facing East). |
"Faculty Room" walls
come down; in the space formerly occupied
by the Main Office, walls are removed to make space for two
2nd grade homerooms. |
5/2/07:
 |
|
View from the
2nd floor hallway,
looking North.
|
Top floor looking north towards terrace.
|

View of main middle school
entrance from courtyard. |
View South from terrace
toward classroom. |
4/5/07: Framing

Final ceiling beams
in the top-floor classroom on the North side of the new building.
|
View (from
Library) of future site of front stairs up to Main doors of
the new Middle
School. Black waterproofing covers the ceiling of the data and
electrical rooms. |
3/15/07: Steel Beams Go In!
| Students sign one of the beams. |
The beam is installed in the new building! |

View North through the framing. Plywood
flooring covers the multi-purpose room. |
Metal decking is
welded to the 2nd floor steel beams. The deck is a form
for concrete that will be poured on top. |
Rebar,
for strength, is tied in a crossing pattern is laid on the metal
decking before the concrete is poured. |

Concrete
is pumped into the area then is formed by hand (2nd floor).
|
Concrete finisher using a walk-behind
power trowel to finish the floors (2nd floor). |
View North from
the 3rd floor. |
2/22/07: Multi-Purpose Room
and Elevator Take Shape/Steel is Delivered!

Underground
duct work for heating and air conditioning system in multi-purpose
room.
|
Ground floor
pre-concrete. |
Poured concrete
slab floor on ground-level multi-purpose room. |
| Elevator shaft in progress. |
Completed elevator shaft.
|
|

| The first load of steel. |
Top layer of asphalt has been applied
on newly widened Fourth Avenue. |
1/5/07: Shotcreting (Concrete
applied with a pneumatic hose)

Once
shotcrete is applied, worker scrape excess with a large
screed (upper left) then follow with trowels to smooth down
walls to the final surface (lower right). |
Looking at the main building from
the approximate location of the main door to the new middle school
building. |
Looking
NE at the ground floor of the new middle school building.
This will be the area of the multi-purpose
room.
|
Close-up off
wall getting shotcrete. The bottom half
has been finished; another level of shotcrete will be applied
to the top. Steel
rebar
is
embedded
in
the concrete
to add strength. |
Workers shotcrete
an exterior walls of the new middle school building. Worker
on the left has an air hose to blow away loose debris so the
concrete can have the best surface to adhere to. Worker
on the right has the shotcrete gun. |
11/20/06:
Stairs leading from the Nob Hill turnaround
to the lunchroom ready
to be poured.
|
Sections of the Nob Hill street turnaround
being poured. |

The
pump operator controls both the movement of the crane and concrete
flow with the wireless controller strapped
around his waist. |
The foundation
of the electrical transformer pad is poured. The concrete
pumper fully extended can reach 150’ in five sections. |
The east wall of the new playground getting some much
needed fill placed for drainage. |
Workers applying some drain mat to the foundation of the new middle
school (the black mat in the lower right). A water proof product
will be applied over this. |
The trench that is filled with water in this photo will feed the
electrical service from Fourth Avenue to the new electrical room. |
10/19/06: Paving

Laying the asphalt for the
new NE parking lot.
|
Laying out the concrete forms for
the Nob Hill turnaround. |

A view of the south wall of the
new middle school building. |
Laying
the asphalt on the new access drive. |
9/29/06: Soil Nailing and Pouring Concrete

Boring
holes into the hillside
|
View of finished
soil nail rows on the south end of the new middle school building.
|

Project team stands at the new elevation of Nob Hill turnaround,
where the street level has been lowered approximately
four feet.
|
Concrete pumper
truck pumping concrete into those hard to reach places. |

Cast in place concrete wall forms awaiting concrete at the north
edge of new access drive. |
Concrete is pumped into forms. |
Finished concrete wall
two days after
pour.
|
|
Concrete truck passes concrete to another truck which
pumps it up the arm (green) and down the chute.
8/24/06:
Retaining Walls
The future parking lot at Fourth and Newell
begins to take shape.
Between the two new walls (where the backhoe is working) is where
the new
play court will be. |
This view is looking up from the level of the new play
court.
|

Our superintendent Mike Horgan (L) and
foreman
Ryan Gellerson (R) take a
moment to show their faces. |
The rear deck of the Nob Hill
house is framed
up and ready to be completed.
|
8/10/06: Utility Preparations

This is the segmental retaining
wall which
will separate the new access drive from
the house we are converting to administrative use. Stairs will connect
the drive to the deck on the back of the house. |
This is the trench that was dug
for the
new fire line water service. It’s about 11’
deep and goes about 4’ underneath the
building before coming up through the
existing floor. |

This trench measures 3’ wide by 3’ deep
and will contain electrical feeds from the new middle school building.
The
old electrical service entrance will be replaced by a new one on Fourth
Avenue.
7/24/06: Grading and Excavating
These photos give an idea of how deep we have to
dig to build a good base for the new driveway. The
excavators
have dug down until
they hit soil firm
enough to lay down the bed of crushed rock. Utility
piping will be
laid on top of the tamped rock.
After excavating approximately 10 feet down, this manhole
is level and ready to be connected and backfilled around.
7/10/06: Site Preparation

Fencing
will shield the academic buildings for the duration of the school year
from the excavation and construction.

Water
utilities are moved into place at
corner of Newell St and 4th Avenue
N.
5/12/06: Demolition

Demolition of the house on the East side of Nob Hill Avenue
N.

Demolition
of the house at the corner of Newell St & 4th Avenue N.
Back to Facilities Homepage
|